The original transformer was installed in 1984. Due to a build-up of flammable gasses, the unit failed gas-inoil analysis completed by SD Myers, so a replacement was required. Chief Ethanol needed:
- Minimal downtime
- Exact transformer replacement
- Exact HV load interrupter switch replacement
- Engineering support
PSC RRU | Competition | |
Unit | $60,000 | $45,000 ($15K cost Delta) |
Install | $5,000 (six hours) | $10,000 (12 hours) |
Cost total | $65,000 | $55,000 |
Downtime saved | $60,000 (6hrs X $10K/hr) | |
Cost comparison | $65,000 | $115,000 |